FLORIDA'S TURNPIKE WIDENING
FROM NORTH OF EUREKA DRIVE TO SOUTH OF KILLIAN PARKWAY
CMEMC - Construction Management Engineering & Materials
SCOPE OF WORK
As a member of the WSP Team, Castillo Engineering provided Construction Management for the widening of Florida’s Turnpike Extension/SR 821 to eight and 12 lanes. Sound barrier walls will be built along qualifying residential areas along both sides of the Turnpike. The Turnpike/State Road 874 interchange will be realigned. Work also includes asphalt milling and resurfacing, bridge widening, landscaping, drainage, lighting, signage and traffic signal improvements on local roads.
CLIENT
Florida's Turnpike Enterprise
LOCATION
Miami, Florida
PROJECT COST
$145.3 Million